|
|
|
|
Who Pays When Unmarked Utilities Are Hit
|
|
by Bernard S. Kamine
|
ECA Legal Counsel
|
|
Beneath every modern city is a complex web of water, sewer, storm drain, gas, oil, steam, electric,
telephone, fiber optic and cable lines that are laid alongside, across, over and under each other. Whenever the
surface is scratched a line can be hit. When hit, a line can be damaged and produce hazards. Containing those
hazards and repairing the line often shuts down adjacent construction activity, causing delay damages (e.g., labor
and equipment standby, extended field overhead, need to accelerate to get back on schedule). Several California
statutes, in different codes, address these issues; common law doctrines can also be involved. Some of the
statutes affect parties to the construction contract; others affect the contractor and third parties. Anyone who breaks
the ground surface must understand both the statutory duties and when damages can be recovered under either the
statutes or common law doctrines.
|
One statute, Government Code § 4215, requires public agencies to "assume the responsibility,
between the parties to the contract, for the timely removal, relocation, or protection of existing main or trunkline utility
facilities located on the [project] site . . . if such utilities are not identified . . . in the plans and specifications made a
part of the invitation for bids." The contractor must be compensated for relocation and repair costs, and "for
equipment on the project necessarily idled during such work." Also no liquidated damages can be assessed for
delays resulting from hitting, repairing and relocating a main or trunkline not shown on the plans.
|
|
|
|
|
Another statute is the Regional Notification Center System (Gov. Code § 4216 et seq.), often referred to as the
Underground Service Alert (USA) or Digalert statute. It uses the term "operator" to cover any person, business,
public agency or other entity "which owns, operates, or maintains a subsurface installation." The only exception is
installations on private property that serve only that property and are operated and controlled by the property owner.
If strictly complied with, the USA statute gives contractors a shield. When not followed, it can become a sword for
operators. Its violation can also expose both contractors and operators to civil penalties.
|
"Every operator of a subsurface installation," except Caltrans, is required to join - and help finance -
a regional notification center (Gov. Code § 4216.1). An operator who fails to do so forfeits any claim for damage to
its installations (Gov. Code § 4216.7). There are two regional notification centers: Underground Service Alert of
Southern California (www.digalert.org) and Underground Service Alert of Northern California (www.usanorth.org). Both
use the same call-in number: (800) 227-2600. The 19-person governing board of USA-South has representatives from
16 operators, one contractor, one locating firm and one public member. About 30% of the funding comes from
Sempra Energy and its subsidiaries, like Southern California Gas Company. Most of the call-ins it receives are from
operators or contractors working for operators.
|
|
|
|
|
Except in an emergency, every person planning to conduct any excavation (i.e., using any tools or equipment to
break the surface - even just the removal of sod, a sidewalk or pavement) must contact the regional USA center at
least 2 working days, but not more than 14 calendar days, before starting work. Further, "if practical," the excavation
area should be delineated in white paint; otherwise, it must be sufficiently identified in the call-in to tell the operators
where to mark their lines (Gov. Code § 4216.2). The USA center assigns an "inquiry identification number" to the
call, and notifies the operators. Each operator must "field mark the approximate location" of any lines that may be
affected by the excavation and are shown on its records or can be located using "standard locating techniques,"
(Gov. Code § 4216.3). "Approximate location" means within 24", horizontally, of the line (Gov. Code § 4216). The
contractor must determine the exact location "with hand tools," except for the removal of pavement when no
subsurface installations are contained in the pavement (Gov. Code § 4216.4).
|
The contractor's shield: If a contractor calls-in to the USA center, excavates between 2 working
days and 14 calendar days after the call, yet hits an unmarked utility line that should have been marked, the operator
forfeits any claim for damages caused by its failure to mark the line. However, the USA statute does not shield the
contractor from 3d party claims (e.g., someone injured by flying debris from an explosion when an unmarked gas line
is hit, or property flooded when an unmarked water line is hit) (Gov. Code § 4216.7). Nor does the USA statute give
the contractor a sword to recover its damages from the operator, but other statutes and common law doctrines
discussed below may do so.
|
To preserve the shield, when excavations continue beyond 14 calendar days from the call-in date,
the contractor must "revalidate" the inquiry identification number by calling-in again on or before the 14th day after
the initial call-in, and again on or before the 14th day after the 2d call-in, etc. until the excavation work is finished
(Gov. Code § 4216.2). Otherwise, the shield lapses on the 14th day after the last call-in, and the contractor must
start the process anew, obtaining a new inquiry identification number and waiting two working days before
excavating. In other words, to preserve the shield on any job over 14 calendar days, the contractor must make the
initial USA call and then assure that a revalidation call is made not later than every 14 calendar days thereafter until
the work is finished.
|
The operator's sword: If a contractor fails to call the USA center at least 2 working days before
commencing excavations, it is liable for any damage to utility lines that would have been marked if the contractor had
called or waited the 2 working days after the call. Also, if the contractor uses machines, instead of hand tools, to
determine the exact location of a marked line, it is liable for any damage to that line caused by the use of machines.
(Gov. Code § 4216.7)
|
|
|
|
|
Although the USA statute provides no sword for the contractor to use to recover its damages, the statute does impose
a duty on operators to mark their lines upon notice of a call-in to the USA center. A call-in by any contractor is
sufficient to invoke the duty (in other words, the duty can flow to a prime contractor based on a subcontractor's call-in
or vice versa). The duty flows to any owner representative, design professional or contractor that the operator knows
or should know will be on the project (contrast the contractor's shield which only protects contractors who timely
called-in to the USA center). The duty should exist for as long as the marks would have given notice of the subsurface
installations if they had been properly placed when requested. In other words, the duty can exist for days or weeks
after a 14 day shield period has elapsed, if the marks would have given notice of the line that was hit had the line been
properly marked when the last USA call-in was made. The duty also requires marking the lines in the customary
manner; a line not so marked may, for practical purposes, be unmarked. The industry marking standards are
described in "Suggested Guidelines for Prospective Excavation Site Delineation and Facility Owner Markout," which
can be found on the USA-South web site, and explains, for example, "Marks in the appropriate color should be
approximately twelve (12) to eighteen (18) inches in length, spaced no more than fifty (50) feet apart. The marks
should be placed over the approximate center of the facility."
|
|
|
|
|
If an operator breaches its duty to properly mark lines upon notice of a USA call-in, then the contractor who hit the
unmarked line, and any other contractor the operator could have foreseen on that project, should be able to recover
damages under one of several legal theories.
|
For example, if an operator undertook the marking of lines in response to a USA notice, but missed the one
that was hit, and the hit line was either in the operator's records or could have been located using standard locating
techniques, then the operator was negligent. It is liable to every contractor who could have reasonably been
anticipated to suffer damages from the unmarked line being hit. As Schwartz v. Helms Bakery Limited (1967) 67 C2d
232, 238, 60 CR 510, 430 P2d 68, explains: "Firmly rooted in the common law lies the concept that . . . 'He who
undertakes to do an act must do it with . . . care.' [citations, including Rest. 2d, Torts § 324A] '[I]f the defendant enters
upon an affirmative course of conduct affecting the interests of another, he is regarded as assuming a duty to act, and
will thereafter be liable for negligent acts or omissions . . . .' [citations]." Restatement 2d, Torts § 324A provides:
"One who undertakes, gratuitously or for consideration, to render services to another which he should recognize as
necessary for the protection of a third person or his things, is subject to liability to the third person for physical harm
resulting from his failure to exercise reasonable care to protect his undertaking, if (a) his failure to exercise reasonable
care increases the risk of such harm, or . . . (c) the harm is suffered because of reliance of the other or the third person
upon the undertaking." This well-established common law doctrine has been employed against public utilities in
California (Lurye v. So. Cal. Edison Co. (1999) 71 CA4th 1167, 84 CR2d 225 [rejecting utility's arguments that its
status as a utility made it immune from this doctrine].
|
|
|
|
Another legal theory: Since one purpose of the USA statute is to protect anyone who might be injured or damaged
by the disruption of an underground utility line, including contractors working near the line, a operator's breach of its
statutory duty to mark the line is negligence (Ev. Code § 669). The contractor need only prove that the failure to
mark the line was the cause of the line being hit and the nature and extent of the damages suffered from hitting the
line. To the extent that the owner of the unmarked line is a public utility, this common law negligence theory is
augmented by Public Utilities Code § 2106, which provides: "Any public utility . . . which omits to do any act . . .
required to be done . . . [by] any law . . . shall be liable to the persons or corporations affected thereby for all loss,
damages, or injury caused thereby or resulting therefrom." Government Code § 4216.3 is a law that requires an
operator, when properly notified by the regional notification center, to mark all subsurface installations on its
records or that can be located by standard locating techniques. If an operator fails to do that act, it is liable to
everyone damaged as a result of an unmarked line being hit, whether or not the victims are protected by the
contractor's shield under Gov. Code 4216.7.
|
What about those civil penalties? Under Government Code § 4216.6, any contractor or operator
who negligently violates the USA statute can be sued by the Attorney General or a district attorney or the local or
state agency that issued the building permit for the project for a civil penalty of up to $10,000. The penalty for
knowingly and willfully violating the statute can be as high as $50,000. There is no record of any such lawsuit being
brought. However, if a death results from hitting an unmarked line, the local district attorney may decide to seek
those civil penalties.
|
|
|
|