|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Validity of Liquidated Damages
|
by Bernard S. Kamine
|
ECA Legal Counsel
|
|
Every public works project that overruns the contract time, as extended, enters into the realm of liquidated damages. There
are many reasons why liquidated damages may not be enforced, but they generally involve just a few legal concepts. Whether the prescribed
liquidated damages meet minimum requirements for reasonableness and actual damages. Whether the contract language requires the all-or-
nothing or apportionment-of-delay analysis. Whether liquidated damages are barred by acts or omissions of the owner which prevented timely
performance, amount to a waiver, or estop the owner from enforcement.
|
Actual Damages and Reasonableness
|
Before there can be any liquidated damages, there have to be actual damages. The actual damages must result from a delay in
putting the project into operation. In other words, once the project is sufficiently complete that it can perform its intended function, and the
agency takes over and starts using it, actual damages resulting from delay cease, so liquidated damages must also cease. Liquidated
damages cannot be a penalty for the agency to club the contractor into compliance with punchlist, warranty, paperwork or other requirements
that do not affect the use of the project as contemplated by the contract.
|
|
|
|
Moreover, liquidated damages must be a reasonable attempt to approximate the actual damages. That attempt is judged as of the
date the contract is signed. For example, if a storm drain is not completed on time, the agency suffers by having to provide alternative means
to deal with storm water, plus possible extended inspection costs. The liquidated damages must be forward-looking attempt, as of the day
the contract was signed, to estimate what the dollar amount of those actual damages would be. If the liquidated damages are unreasonable
under that forward-look, they are not enforceable at all (Civ. Code §1671, Pub. Cont. Code § 10226). For example, liquidated damages, that
may be appropriate for a project as a whole, would not be reasonable if the agency attempted to assess them during a plant establishment
period after all other work is completed, when the value of the plants being established is less than the liquidated damages assessment.
Besides, such liquidated damages also amount to a disfavored forfeiture (Civ. Code §§ 1442; Hawley v. Orange Co. Flood Control Dist. (1963)
211 CA2d 708, 713, 27 CR 478; Brawner v. Wilson (1954) 126 CA2d 381, 385, 271 P2d 397).
|
The All-or-Nothing Approach
|
The standard judicial approach to liquidated damages, in any kind of contract, is all-or-nothing (5 Williston on Contracts (3d
ed. 1961) pages 764-66). It is the approach used with construction contracts that contain provisions for only (a) completion by a particular
date and (b) liquidated damages for overrunning that date - in other words, contracts with no provisions for extending the completion date for
events beyond the contractor's control. The first public works contracts reviewed by California appellate courts were of this type, and the all-
or-nothing approach to liquidated damages was applied.
|
In Gogo v. Los Angeles County Flood Control Dist. (1941) 45 CA2d 334, 114 P.2d 65, the contractor overran the completion date by
249 days. In the absence of contract language prescribing conditions under which the completion date would be extended, the district's chief
engineer, relying on the provision: "On all questions relating to . . . the proper execution, progress or sequence of the work. . . . the decision
of the Chief Engineer shall be final and binding," waived 113 days of liquidated damages (for district actions preventing site access,
excavation extra work and inclement weather). However, the trial court remitted all 249 days of liquidated damages. On appeal, the district
sought the liquidated damages for the part of the overrun not waived by the chief engineer. The court held, at 45 CA2d 344-45:
|
|
|
|
In making this contention defendant [district] seeks to have this court apportion the amount of delay attributable to
each [Gogo and the district] and to fix damages accordingly. The correct rule is that where such delays are
occasioned by the mutual fault of the parties the court will not attempt to apportion them but will refuse to enforce
the provision for liquidated damages. [out-of-state citations]. . . . It follows that plaintiffs were properly awarded the
total amount of liquidated damages withheld by defendant.
|
|
|
|
|
|
|
The all-or-nothing approach is appropriate when the contract fails to prescribe the conditions or events that determine which party is
responsible for what delays in the project. For example, absent a contract provision defining the weather risk and allocating it between the
parties, upon what standard did the chief engineer in Gogo, or could a court in subsequent litigation, apportion that risk? The same obtains
for many other risks attendant to public works construction (e.g., earthquake, fire, labor disputes, shortage of materials, freight embargoes
and government actions during emergencies or war).
|
|
|
|
The Apportionment-of-Delay Approach
|
When a contract prescribes events and conditions for which the original contract completion date must be extended, the contract,
itself, provides a mechanism to apportion responsibility between the parties for any overrun of the date: If delay results from specified
events or conditions, the agency must extend the contract time, thereby apportioning delay. The courts can and will enforce that specific
contract language by determining responsibility for discrete delays under the standards established in the contract. The analysis starts at
the contractor's apparent breach of contract by overrunning the original contract completion date (for this breach the agency is entitled to
damages, usually liquidated damages at a specified daily rate). Then the inquiry turns to the agency's breaches by failing to properly
extend the contract completion date. Sometimes the court must first determine whether one of the specified events or conditions
occurred, e.g., did the public agency really order extra work for which a change order should have been issued, including an appropriate
time extension. This analysis of discrete delays under the standards established in the contract often results, in a remission of some or
all of the liquidated damages withheld by the agency.
|
|
|
|
The first California case to discuss apportionment was Nomellini Construction Co. v. State ex rel. Dept. of Water Resources (1971) 19
CA3d 240, 96 CR 682. There, on a contract to build portable houses, the liquidated damages were $10/house/day. The overrun was 6840
house/days. Pursuant to the contract, the state gave Nomellini 2440 house/days in extensions, leaving 4400 house/days of liquidated
damages. Nomellini sued for remission of all liquidated damages. The trial court analyzed the delays, determined that the state not
Nomellini was responsible for all of the delays, and remitted all liquidated damages. The appellate court reversed, holding (at 19 CA3d
246-47): "On the record as it has been represented to this court by the parties in their briefs and in their arguments there were no
disallowed delays for which Nomellini was not responsible." Then the court went on (19 CA3d 245-46):
|
|
|
|
Assuming arguendo contrary to our holding that there were delays which the Department should have allowed, they were
delays which the trial court would have been obligated to apportion. The controlling law is found in . . . Robinson v.
United States, 261 U.S. 486 [67 L.Ed. 760, 43 S.Ct. 420]. That case involved a contract which provided for both
liquidated damages and extensions of time. . . . In holding that apportionment was proper the court stated at page
488 [67 L.Ed. at page 762]: . . . "The law required that some provision for liquidated damages be inserted. . . . The fact
that the government's action caused some of the delay presents no legal ground for denying it compensation for loss
suffered wholly through the fault of the contractor. . . ." This holding . . . did not announce a unique or novel principle. 5
Williston on Contracts (3d ed. 1961) pages 764-766, states: "Where both parties are in fault a party who has contributed
to the breach cannot recover a sum stipulated as liquidated damages, even though performance of the contract is
continued, and the other party is thereafter at fault: . . . In building contracts, there is often inserted a provision giving
the architect power to certify an extension of time in certain cases, by virtue of which the effect of a delay caused by
the owner operates merely as an extension of the time of performance, and a new time is substituted for the old. In that
event though the owner causes delay the builder is liable in liquidated damages, but the period of delay caused by the
owner is deducted from the total delay. Unless the contract contains such a provision the delay due to each party
will not generally be apportioned." [italics in the original; bold face added]
|
|
|
|
In other words, when the contract prescribes events and conditions for which the original contract completion date must be extended, the
courts enforce this language by inquiring into every delay to determine whether it qualifies under the contract language for a time
extension. For example, when a contract provision defines the weather risk and allocates it between the parties, it is that contract
standard which a court enforces by apportioning weather delays accordingly. The same obtains for all of the other risks that are allocated
by the contract time extension clause. The same also obtains for all delays arising out of owner breaches of the contract, e.g.,
interference with the contractor's work on controlling operations.
|
The Waiver/Estoppel/Prevention Theories
|
Independent of the all-or-nothing and apportionment-of-delay approaches are equitable doctrines and principles of
contract law that can also impact upon liquidated damages. These doctrines and principles often overlap with each other and with the
two approaches to liquidated damages.
|
Either party to a public works contract can be prevented from relying upon any requirement in the contract by the
equitable doctrine of estoppel (e.g., Maurice L. Bein, Inc. v. Housing Authority (1958) 157 CA2d 670, 678-82, 321 P.2d 753 [authority
estopped from enforcing both a clause precluding damages for delay and a clause limiting the remedy for agency-caused delay to just an
extension of contract time, i.e., limiting the remedy to just an abatement of liquidated damages]). Thus, an agency can be estopped from
enforcing the liquidated damages clause.
|
Similarly, either party to a public works contract can waive any benefit under the contract (Weeshoff Constr. Co. v. Los
Angeles County Flood Control Dist. (1978) 88 CA3d 579, 589, 152 CR 19 [district waived written change order requirement by forcing
Weeshoff to do extra work, yet, at the time, refusing to admit it was extra work]; accord, Bettelheim v. Hagstrom Food Stores, Inc. (1952)
113 CA2d 873, 878, 249 P.2d 301 [lease provision prohibiting waivers not made in writing was, itself, waived; "[e]ven a waiver clause may
be waived by conduct."]). Once a right is waived, it cannot later be asserted (Carmel Valley Fire Protection District v. Sate of California
(1987) 190 CA3d 521, 534, 234 CR 795 ["A right that is waived is lost forever"]). Thus, an agency can waive all or part of its liquidated
damages.
|
Given appropriate facts, the estoppel or waiver doctrines will apply and result in a reduction of liquidated damages
assessed by an agency. For example, when an agency causes delays, pushing the work beyond the contract completion date, it could
thereby be estopped from enforcing that date and recovering liquidated damages, or its conduct could amount to a waiver of the breach by
overrunning the completion date and the corresponding liquidated damages.
|
Acts or omissions of the agency also can prevent the contractor from completing performance within the contract time. Civil
Code § 1511 provides:
|
|
|
|
The want of performance of an obligation [e.g., completion by the contract completion date] . . . in whole or in part, or
any delay therein is excused by the following causes . . . [¶] 1. When such performance. . . is prevented or delayed by
the act of the creditor . . . even though there may have been a stipulation that this shall not be an excuse. . . .
[boldface added]
|
|
|
|
A public agency is such a "creditor" (Peter Kiewit Sons' Company, supra, 59 Cal.2d at 243-44).
|
This excuse/prevention principle is actually the underlying theoretical support for both the all-or-nothing and
apportionment-of-delay approaches. The delays for which the agency is responsible prevent or delay completion by the original contract
completion date. That is why completion by that date is excused, and liquidated damages remitted - either all of them (because there is
no vehicle in the contract to apportion them) or the apportionable amount (according to the terms of the contract).
|
On the other hand, neither the all-or-nothing approach nor the apportionment-of-delay approach is the only application of
the excuse/prevention principle. Nor do they affect the doctrines of estoppel or waiver. There are many other applications of the
excuse/prevention principle, some of which impact upon liquidated damages issues. As Kenworthy v. State of California (1965) 236
CA2d 378, 382, 46 CR 396, points out:
|
|
|
|
|
In Peter Kiewit Sons' Co. v. Pasadena City Junior College Dist., 59 Cal.2d 241 [28 CR 714, 379 P.2d 18], it was
held that where a contractor is delayed in the construction of a building by acts of the owner, he is entitled to an
extension of time to complete equal to the delay. Although this rule was stated in a case in which the question
was whether the contractor was relieved from the burdens of a liquidated damage provision of a contract, the
reason for the rule should be equally applicable to any case where a question of the contractor's excuse for
nonperformance within a time fixed by the contract is properly raised. [boldface added]
|
|
|
|
|
|
|
|
Defendants' principal contentions concerning these change orders are . . . That the change orders recited
that there was to be no change in the contract time, and the contract itself provided that no extension of
time would be granted. However, order 3 was dated February 1, which was after the contract date of
completion. It necessarily was a waiver of the time set for completion [citation]." [boldface added]
|
|
|
|
|
In Aetna Cas. & Surety Co. v. Board of Trustees (1963) 223 CA2d 337, 35 CR 765, the school board assessed liquidated damages for
the 125 day overrun of the October 3, 1958 extended contract completion date. The contractor's surety sought to set them aside.
The contractor was advised of changes on September 3 and September 29, 1958, but told not to perform the new work until it was
approved by the State Department of Finance. Notice of the approval issued on January 6, 1959, and the contractor proceeded with
the work. In other words, "as a result of the timing of change order 3B, the contractor would have been unable to complete the project
by October 3, 1958, through no fault of his own" (223 CA2d 339). explained (223 CA2d 340):
|
|
|
|
|
The facts indicated above clearly establish that while the contractor was behind in the overall job on
October 3, 1958, the District, by its own conduct in processing the change orders, rendered performance
impossible within the extended time agreed upon by the parties. The District contends that since there
was no evidence that it caused any delay in the ultimate completion of the entire project, it should be
allowed liquidated damages. We do not agree. The crucial date is that stipulated for completion
|
|
|
|
The trial court had apportioned the liquidated damages, charging the contractor only with the overrun after January 6, 1959, when the
change orders were approved by the Department of Finance. The appellate court criticized this apportionment (223 CA2d 340),
because "a proper apportionment would necessarily have to allow the contractor a reasonable time beyond the change order
notification on January 6, 1959, within which to complete the work called for." But, ultimately, the appellate court applied the all-or-
nothing approach to reject all liquidated damages.
|
By issuing change orders that require extra work after the extended contract completion date, an agency can waive the
contract completion date until that work is completed, can waive liquidated damages to the same date, can be estopped from
enforcing liquidated damages to that date, or has prevented the contractor from completing by that date.
|
|
|